Rieste Construction Update: The First Building Columns Are in Place
With the site work completed on schedule, the first building columns are now in place. The structural frame of the new buildings is expected to be completed in just a few weeks.
Last week, the first six building columns were delivered and installed. The roof trusses have also arrived at the construction site.
The structural frame of Buildings 4 and 5 is expected to be completed in about 14 days. Work on the roof and facade will begin afterward. The building’s exterior is expected to be fully enclosed by the end of December.
The expansion is now visible at the existing building, too: The Zerhusen Kartonagen lettering has been removed from its rear wall. This is exactly where the extension will connect.
With approximately 8.000 m² of additional building space, Zerhusen Kartonagen is laying the groundwork for further growth at its Rieste site. Completion is planned for Summer 2027.